Programmes

Step by step

For a walkthrough with screenshots, see Plan across teams with a programme.

A programme plans work across several teams' projects. It holds initiatives: outcomes the teams work toward together, such as Self-serve checkout. Each team keeps planning in its own project, with its own board, backlog, sprints and releases. The one link across projects is an epic's parent: an epic in a team project can belong to one of the programme's initiatives.

The programme then shows:

  • each initiative's epics, team by team;
  • how much of the work under them is done;
  • when it is likely to finish;
  • what is late or blocked by another team.
Programme CHK                Team PLAT                 Team WEB
  CHK-1 Self-serve checkout ── PLAT-14 Order API  ──┐
                            └─ WEB-3 Checkout redesign ── WEB-21 Card form …
                                       stories, sprints and boards stay in each team

Setting one up

  1. Create a project from the Programme template (Projects → Create project). It comes with:
  2. an Initiative issue type (level 2, above epics), with a Proposed → In Progress → Done workflow;
  3. an Action type for the programme's own tasks, with an Actions board;
  4. risks and decisions, for programme-level risks and decisions (see risks-decisions.md).
  5. In the programme's Settings → Teams, add the team projects. Only the programme's admins can add teams, and only projects they can browse. Service projects and other programmes can't be teams.
  6. Create initiatives on the Roadmap tab (New initiative).
  7. Give each epic its initiative:
  8. on the epic, with the Initiative field in its details;
  9. when creating an epic, with the Initiative picker;
  10. from the roadmap's list of team epics under no initiative.

A programme's tabs are Roadmap, Timeline, Dependencies, Board (its actions), Issues, Risks, Decisions and Reports. A team project lists the programmes it belongs to on the API (GET /projects/{key}/programmes), and its epics' Initiative field offers their initiatives.

The hierarchy

Level Type Where
2 Initiative The programme
1 Epic A team project, under an initiative or not
0 Story, task, bug The epic's project
-1 Sub-task Its parent's project
  • Crossing projects: only an epic's parent may be in another project. That parent must be an initiative of a programme the epic's project is a team of. Everything below an epic stays in the epic's project, so boards, sprints, the backlog and ranking work as before.
  • Moving an epic: an epic can move from one initiative to another, in the same or another programme. Its history records each change with the initiatives' keys.
  • Removing a team: taking a team out of a programme unlinks its epics from the programme's initiatives. The settings page asks first, and each epic's history records it.
  • Deleting: deleting an initiative, or the whole programme, leaves the team epics in place, without an initiative.

Who sees what

Being one of a programme's teams gives nobody access to anything. Everything a programme shows is limited to what the viewer can already browse.

Someone who can… Sees
Browse the programme but not a team The team counted ("1 team you can't browse is left out"), never named. None of its epics or work, and no progress from it
Browse a team but not the programme The team's epics without their initiative: the epic says "An initiative you can't see". They can't change or remove it (403) and can't pick that programme's initiatives
Browse both Everything

A dependency on an issue the viewer can't browse is counted, not named: "Blocked by 1 unfinished issue in a project you can't see".

Roadmap

The Roadmap tab lists the programme's open initiatives in rank order (Show done adds those finished in the last 90 days). Each initiative shows:

  • Progress: the issues under its epics, in the teams the viewer can browse, by status, with story points.
  • Due date and forecast. An epic's forecast is the latest due date of the epic and the issues under it. An initiative's forecast is the latest of its epics'. The forecast shows in red when it is after the due date.
  • Its epics, team by team, each with its own progress, forecast and flags.

The flags:

Flag On an epic On an initiative
Late Its forecast is after the initiative's due date Some of its epics are late
Overdue Its due date has passed and it isn't done The same
Unscheduled No dates, and no due dates under it No dates, and no forecast from its epics
Blocked It or an issue under it is blocked by unfinished work in another project Some of its epics are blocked

Below the initiatives, Team epics under no initiative lists the teams' open epics that don't yet say which initiative they serve. People who can edit an epic can link it to an initiative from there.

Timeline

The programme's Timeline nests each initiative, the team epics under it and their issues. It then lists, team by team, the epics under no initiative and issues with no epic. Dates roll up:

  • an epic without dates spans its issues;
  • an initiative without dates spans its epics.

Dependency arrows work across teams. An issue that blocks, or is blocked by, an issue the timeline doesn't show gets a warning naming it, or saying it is in a project the viewer can't browse. Everything else works as on a project's timeline; the API is in api.md.

Dependencies

The Dependencies tab shows who waits on whom:

  • a matrix of unfinished blocks links between the programme's projects, with blocking teams in the rows and blocked teams in the columns;
  • each link, listing first the ones whose dates clash (the blocker ends after the blocked issue starts);
  • what the programme's issues wait on, or hold up, outside it.

Reports

The programme's Reports cover the programme and its teams (those the viewer can browse):

  • open work by team;
  • cumulative flow;
  • created vs resolved;
  • cycle time.

Velocity and sprint reports stay with each team, whose sprints differ. Any dashboard gadget can cover the same projects with project in programmeProjects("CHK").

Query Matches
initiative = CHK-1 Everything under the initiative: its epics, their issues and sub-tasks, in every team
initiative is EMPTY Issues with no initiative above them
issue in descendantsOf("CHK-1") Everything below any issue (three levels down at most)
project in programmeProjects("CHK") The programme's own issues and its teams'

epic = KEY means epics only: an initiative is not an epic, and an epic under an initiative has no epic of its own. Like every issue key in a query, the key in these only matches issues the viewer can browse.

Automation

A rule acts in its own project. An action whose target is the parent or the children skips those in another project, and the rule's run log says so: "skipped 1 parent in another project".

  • A team's rule that rolls dates up to an epic's parent leaves the initiative alone.
  • A programme's rule doesn't change team epics.
  • Roll up dates counts only children in the rule's project.

The roadmap's forecast shows when an initiative is likely to finish without changing its dates.

API

GET /projects/{key}/programme?doneDays=90 The roadmap: initiatives, their epics, progress, forecasts and flags, and team epics under no initiative
GET /projects/{key}/programme/teams The teams the caller can browse and how many others there are
POST /projects/{key}/programme/teams {"projectKey": "WEB"} Add a team (programme admins)
DELETE /projects/{key}/programme/teams/{teamKey} Remove a team; returns how many epics were unlinked
GET /projects/{key}/programmes The programmes a project is a team of
GET /timeline?programme=CHK The programme's timeline. externalLinks lists dependencies on issues it doesn't show
PATCH /issues/{epicKey} {"parentKey": "CHK-1"} Put an epic under an initiative (null takes it out)

The MCP server's get_programme tool reads the roadmap; see mcp.md.