Time tracking

Issues carry an original estimate and a remaining estimate, and people log work against them. Time spent is the sum of an issue's worklogs. Estimates and time show in the issue view, on board cards, in searches, in the sprint report (in hours) and on the timesheet.

Durations

Durations are written the way people say them: 30m, 2h, 1h 30m, 1.5h, 1d, 1w 2d 3h. Units are w (weeks), d (days), h (hours) and m (minutes); full words (2 days, 3 hours) work too, units may come in any order and a bare number is minutes. A day and a week are the working day and week:

Variable Default
WFM_TIME_HOURS_PER_DAY 8 hours in 1d (more than 0, at most 24; 7.5 is fine)
WFM_TIME_DAYS_PER_WEEK 5 days in 1w (more than 0, at most 7)

So with the defaults 1w 2d is 56 hours. Changing the settings changes how stored durations are displayed, not the durations themselves: everything is stored in seconds. The UI reads the settings from GET /api/v1/time-tracking/settings; the parser and formatter exist in Go (internal/timetrack) and TypeScript (web/src/lib/duration.ts) with the same rules and tests.

Estimates

Set them in the issue's Time tracking panel (click a value to edit it), or through the API as originalEstimate and remainingEstimate (seconds) on POST /issues and PATCH /issues/{key} (null clears one). Setting an original estimate on an issue without a remaining estimate sets the remaining estimate to the same value. Changes are recorded in the issue history.

The panel's bar shows time logged (blue) and remaining (grey) against the original estimate. When logged plus remaining goes past the estimate, the part beyond it turns red, the estimate is marked on the bar and the panel says by how much the issue runs over.

Logging work

Log work (in the panel or the Work log tab of the activity section) asks for the time spent, when the work was done (default now, at most a day ahead), an optional description, and what to do with the remaining estimate:

Option Remaining estimate
Adjust automatically (default) goes down by the time logged, never below zero; unchanged if the issue has none
Set to the value you enter
Leave unchanged as it was

Editing a worklog's time with automatic adjustment moves the remaining estimate by the difference; deleting a worklog puts its time back (?adjustEstimate=leave keeps it, and ?remainingEstimateSeconds= sets it).

Permissions: whoever can edit the issue can log work on it (issue.edit for issues you reported or are assigned to, issue.edit_others for the rest). You can change or delete your own worklogs while you can work on the project's issues; project admins can change anyone's. Automation rules cannot log work.

Every worklog added, changed or deleted is recorded in the history (worklog, with the durations) along with any remaining estimate change, bumps the issue's version and fires an issue.updated event with fields: ["timeSpent"] (plus "remainingEstimate" when it changed), so boards and open issue views refresh live and automation rules on field changes can react.

Where it shows

  • Board cards: add the Time tracking card field (board settings, or Configure board on the board). Cards show time logged of the original estimate (3h / 1d, red once over), else the remaining estimate (5h left) or the time logged.
  • Search (search.md): originalEstimate, remainingEstimate and timeSpent compare with durations (remainingEstimate > 4h, timeSpent >= "1d 2h", originalEstimate is EMPTY) and can be ordered by; worklogAuthor = currentUser() and worklogDate >= startOfWeek() find issues by their worklogs.
  • Workflows and automation: CEL conditions see issue.originalEstimate, issue.remainingEstimate and issue.timeSpent in seconds (0 when unset), e.g. a validator issue.timeSpent > 0 on a Done transition.
  • AI assistants: get_issue shows the time tracking and log_work logs work (mcp.md).

Sprint report in hours

The sprint report (Reports page, and the sprint burndown, burnup and health dashboard gadgets) has an Hours measure next to story points and issues:

  • Committed — the remaining estimate of the sprint's open issues when it started.
  • Remaining each day — the remaining estimate of the issues in the sprint that are not done, replayed from the estimate history. Completing an issue burns what was left of its estimate.
  • Logged — time logged on the sprint's issues while they were in the sprint, counted when it was logged (the moment the remaining estimate moves with it).
  • Scope (burnup) — logged plus remaining, so it moves only when work is re-estimated, added or taken out, not when work is logged with the estimate adjusted.
  • Added / removed — the remaining estimate of issues that joined or left after the start, at the time they did.

GET /api/v1/sprints/{id}/report returns these as committedSeconds, completedSeconds, addedSeconds and removedSeconds, and per day remainingSeconds, completedSeconds, scopeSeconds and idealSeconds.

Timesheet

Timesheet (in the sidebar, or from a project's Reports page) totals the time logged per person per day for a week or a month, in hours, on every project you can browse or on one, for everyone or one person. Open a person's row to see the issues. Days are counted in your browser's time zone, by when the work was done. Export CSV downloads the sheet: a row per person and issue with hours per day, a total row per person and a grand total.

GET /api/v1/worklogs?from=2026-10-19&to=2026-10-25&projects=PLAT,OPS&user=<id>&tz=Europe/London returns {dates, dayTotals, total, people: [{user, days, total, issues: [{issue, days, total}]}]} (seconds), covering at most 366 days. Worklogs on issues you cannot browse are left out.

API

Endpoint
GET /time-tracking/settings {hoursPerDay, daysPerWeek}
GET /issues/{key}/worklogs the issue's worklogs, in the order the work was done; each says whether you can change it (canEdit)
POST /issues/{key}/worklogs {timeSpentSeconds, startedAt?, comment?, adjustEstimate?: auto\|leave, remainingEstimateSeconds?}
PATCH /worklogs/{id} change time, start or comment, with the same estimate options
DELETE /worklogs/{id}?adjustEstimate=&remainingEstimateSeconds= delete; the time goes back on the estimate unless left
GET /worklogs?from&to&projects&user&tz timesheet

Every issue in the API has timeTracking: {originalSeconds?, remainingSeconds?, spentSeconds}.